Our lot, February 15, 2015 |
![]() |
First day of "work" on our property. June 4, 2015 |
![]() |
The weeds have grown! June 12, 2015 |
![]() |
We have a mailbox! June 16, 2015 |
![]() |
They dug the hole! June 17, 2015 |
![]() |
Footings are in! June 19, 2015 |
![]() |
Foundation walls are up. June 27, 2015 |
![]() |
Foundation back-filled and awaiting framing! July 2, 2015 |
![]() |
Out for a run and stumble upon this!!! July 7, 2015 |
![]() |
First day of framing. July 7, 2015 |
![]() |
Framing Progress. July 9, 2015 |
![]() |
Note we have a street light by us...more framing work. July 11, 2015 |
![]() |
Making good progress...it's a bit wet inside, though! July 16, 2015 |
![]() |
One day of framing left. July 19, 2015 |
![]() |
Last day of framing, but basement is still wet from rain. Windows and doors are in. July 20, 2015 |
![]() |
Walking into kitchen from mudroom. |
![]() |
Walking into main level from entry hallway. |
![]() |
Entry hallway facing front door/front yard. |
![]() |
Entry hall at stairs, front bedroom & bath. |
![]() |
Lauryn's room! |
![]() |
Back of house! July 20, 2015 |